WIN-370-4 (Section 36 Wind Farm)
https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=122449
Land At Craiginmoddie, Dailly, South Ayrshire, KA26
598458
231426
Application For Consent Under S36 Of The Electricity Act 1989 And Deemed Planning Permission Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 For Installation Of A Wind Farm Comprising Up To 14 Wind Turbines Of Up To 200M To Tip Height And
Associated Infrastructure And Battery Storage Of
7 Mw - Craiginmoddie Wind Farm
92.00
South Ayrshire Council
Site Inspection, Further Written Submission, Inquiry, Hearing
Report
Decision issued
Mr Keith Bray
Rosie Leven, Mr Gordon S Reid
12 Jun 2023 at 09:00
11 Dec 2023
05 Nov 2025 (Application Granted)
**Case Update – 06/11/2025**
The decision on this case has been issued. The case has been allowed and consent has been granted.
Wind Farm (two or more turbines),
Battery Storage,