Carrick Wind Farm, Approximately 6Km South Of Straiton, South Ayrshire, KA19
237186
Application Under S36 Of The Electricity Act 1989 To Install And Operate Carrick Wind Farm Comprising 13 Turbines, With A Blade Tip Height Of Up To 200M, And An Overall Generating Capacity Of Around 86 Mw, And Associated Infrastructure.
South Ayrshire Council (N/A)
Site Inspection, Further Written Submission, Inquiry, Hearing
Mrs Rosie Leven, Mr Gordon Reid
24 Mar 2023
16/05/2023 at _TBC
30/05/2023 at Virtual Meeting
01/06/2023 at _TBC
07/06/2023 at Virtual Meeting
08/06/2023 at Virtual Meeting
19/06/2023 at _TBC
20/06/2023 at Virtual Meeting
26/06/2023 at _TBC
**Case Update – 07/03/2023**
Case conjoined - WIN-370-4&5&6. PEM held 10 Jan. FWS commenced. Second PEM 24 March 2023. Inquiry/hearing sessions May/June 2023. Reports expected October 2023.