PPA-270-2322 (Planning Permission Appeal)
https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=128419
Land 2430M Sw Of Loch Buidhe, Bonar Bridge, IV24
897458
265053
Carnaig Substation - Construction And Operation Of A 400Kv Substation And Associated Infrastructure, Site Access, And Landscaping
Planning permission
Highland Council (24/05062/FUL)
09 Jan 2026
Scottish Hydro Electric Transmission plc
Written Submission, Further Written Submission
18 Nov 2026 (Application Granted)
**Case Update – 18/11/2026**
Scottish Ministers have considered this case and have approved planning permission for the proposal.
Substation/Transmission Line/Pipeline,