TRL-130-1 (Section 37 Transmission line)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=122768
 Site Located Between Proposed Creag Dhubh Substation And The Existing Scottish Power Energy Networks, (Spen) 275Kv Overhead Line (Ohl) From Dalmally To Inverarnan, Near Glen Lochy, (Succoth Glen), Argyll & Bute, PA32
 -5.0950896
 56.329226
 719509
 208739
 13.3 Kilometre (Km) Double Circuit 275 Kv Ohl, Supported By 48 Lattice Steel Towers Between A Proposed Substation At Creag Dhubh To The Existing Spen 275 Kv Ohl, Known As The Yw Route, That Runs From Dalmally To Inverarnan, Near Succoth Glen (Glen Lochy);
 14 Nov 2022
 Argyll and Bute Council (N/A)
 Scottish Hydro Electric Tranmission Plc
 Inquiry
 Report
 Report Issued
 Davidson, Rebecca (Tel: 01312448263 - Email: Rebecca.Davidson@gov.scot)
 Mr David Buylla
 10 Feb 2023
 24 Dec 2023
 **Case Update – 23/11/2023** A report for this case has been submitted to Scottish Ministers. A decision by Scottish Ministers will be made in due course.
 Substation/Transmission Line/Pipeline,
 
contains

  • <<
  • <
  • 1
  • 2
  • 3
  • 4
  • >
  • >>
  • Displaying Results 0 - 10 of 40
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
28 Jun 2023 28 Jun 2023 Correspondence DPEA to participating parties Advising the reporter has sufficient information on these subjects so no further documents will be accepted 0.39MB (URL Details)
23 Jun 2023 27 Jun 2023 Correspondence I Kelly obo of Argyll and Bute Council Advising the Reporter on the Argyll and Bute LDP2 Adoption outcome 0.11MB (URL Details)
13 Jun 2023 13 Jun 2023 Correspondence DPEA and participating parties Exchange confirming why the agendas have not been issued sooner 0.34MB (URL Details)
13 Jun 2023 13 Jun 2023 Correspondence DPEA to participating parties Advising the reporter is willing to accept NMP 14 and 15 0.36MB (URL Details)
13 Jun 2023 13 Jun 2023 Correspondence DPEA to participating parties Advising the reporter will discuss with parties at the inquiry week if a conditions session is necessary 0.37MB (URL Details)
13 Jun 2023 13 Jun 2023 Correspondence DPEA to participating parties Confirming that the reporter has sufficient information about the project-specific need so no further process will be necessary 0.32MB (URL Details)
08 Jun 2023 08 Jun 2023 Correspondence DPEA to participating parties Exchange advising USB are not necessary for the hearing sessions 0.40MB (URL Details)
08 Jun 2023 08 Jun 2023 Correspondence DPEA to Interested Party - No More Pylons Exchange advising replacement links are required for NMP's documents url links 0.23MB (URL Details)
07 Jun 2023 07 Jun 2023 Correspondence DPEA to Interested Party - No More Pylons Exchange advising a decision will be considered once NMP's statements are submitted 0.25MB (URL Details)
07 Jun 2023 07 Jun 2023 Correspondence DPEA to Interested Party - No More Pylons Exchange apologising for the missed correspondence and advising reporter is content to receive the Evening Hearing Statements shortly 0.28MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • 2
  • 3
  • 4
  • >
  • >>
  • Displaying Results 0 - 10 of 40