TRL-170-2 (Section 37 Transmission line)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=122045
 Kendoon To Tongland 132Kv Reinforcement (Ktr) Project – Carsfad To Kendoon, Approximately 5Km North And 7Km North Of, St John’S Town Of Dalry, DG7 3SX
 -4.1895952
 55.143249
 585400
 260540
 Consent Under S37 Of The Electricity Act 1989 And Deemed Planning Permission Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 To Install And Keep Installed Overhead Electric Lines Described Collectively As The Kendoon To Tongland Reinforcement Project In Dumfries And Galloway Planning Authority Area
 01 Feb 2022
 Dumfries and Galloway Council (N/A)
 Ms Magdalena MacLean
 SP Energy Netwroks
 Site Inspection, Further Written Submission, Inquiry, Hearing
 Report
 Report Issued
 Bell, Colin (Tel: 0131 244 6902 - Email: colin.bell@gov.scot)
 Ms Katrina Rice
 Mr David Buylla
 30 Nov 2022 at 9:00
 20 Mar 2023
 **Case Update – 07/02/2024** A report for this case has been submitted to Scottish Ministers. A decision by Scottish Ministers will be made in due course.
 Substation/Transmission Line/Pipeline,
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 5 of 5
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
25 Nov 2022 19 Jan 2023 Representation Burrell, Catherine Representation Redacted 954 Objection 0.11MB (URL Details)
25 Nov 2022 19 Jan 2023 Representation Twynholm Community Council Representation - Twynholm CC_Redacted 0.17MB (URL Details)
14 Oct 2022 19 Jan 2023 Representation McClymont, Alexander Representation Redacted 953 Objection 0.10MB (URL Details)
09 Oct 2022 27 Oct 2022 Representation Interested Party Mr and Mrs Bowden 0.10MB (URL Details)
23 Aug 2022 24 Aug 2022 Statement Agent - Shepherd & Wedderburn LLP Comments on representation from Gatehouse and Kirkcudbright Angling Association 0.39MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 5 of 5