PS-270-1 (Power Station)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=120883
 Located Approximately 14Km South West Of Inverness, Land 630M East Of Park Cottage, Dores, Inverness, IV2
 -4.3326804
 57.381782
 834777
 259860
 The Proposed Red John Pumped Storage Hydro Scheme Comprising Of An Electrical Generating Station With A Capacity Of More Than 50Mw, Located Approximately 14 Km South West Of Inverness
 24 Jan 2020
 Highland Council (18/05427/S36)
 Mr Fraser Mitchell
 ILI (Highlands PSH) Ltd
 Further Written Submission, Inquiry, Hearing
 Report
 Decision issued
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 Ms Claire Milne
 19 May 2020
 04 Sep 2020
 07 Jun 2021 (Application Granted)
 Hydro/Solar Power,
 
contains

Click table headers to sort table