 An Application Under Section 36 Of The Electricity Act For The Construction And Operation Of Oliver Forest Wind Farm, Total Of Seven Wind Turbines With A Maximum Blade Tip Height Of 200 M, Foundations, Crane Hardstandings And Adjacent Laydown Areas, Access Tracks, Watercourse Crossings, Temporary Borrow Pits, Temporary Construction Compounds, Substation And Control Building, Battery Energy Storage System, Ancillary Infrastructure And Heritage Footpath.
 7
 200.00
 73.40
 09 Sep 2025
 Scottish Borders Council (NA)
 Winston Roberts
 Oliver Forest Wind Farm Limited
 Inquiry, Hearing
 Report
 Allocated to reporter
 Cowie, Karen (Tel: 0131 244 6936 - Email: Karen.Cowie@scot.gov.uk)
 Tammy Swift-Adams
 10 Sep 2026
 16/09/2026 at Tweedsmuir(nr Biggar) Village Hall
 04 Nov 2026
 **Case Update – 12/06/2026** One further written information request is currently outstanding. Invited parties are entitled to comment on the information submitted in relation with the further written submission request.
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • 2
  • >
  • >>
  • Displaying Results 0 - 10 of 20
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
13 Apr 2026 13 Apr 2026 Correspondence DPEA to all participating parties Attaching note of pre-examination meeting of 01 April 2026 0.18MB (URL Details)
10 Apr 2026 10 Apr 2026 Note of Meeting DPEA Note of pre-examination meeting of 01 April 2026 0.18MB (URL Details)
25 Mar 2026 25 Mar 2026 Agenda DPEA Pre-Examination Meeting Agenda 0.14MB (URL Details)
25 Mar 2026 25 Mar 2026 Correspondence DPEA to participating parties Attaching PEM Agenda 0.14MB (URL Details)
23 Jan 2026 26 Jan 2026 Response Tweedsmuir Community Council Exchange confirming availability 0.15MB (URL Details)
23 Jan 2026 26 Jan 2026 Response Morton Fraser MacRoberts LLP Exchange confirming availability 0.20MB (URL Details)
23 Jan 2026 26 Jan 2026 Response Pinset Masons OBO Applicant Exchange confirming availability 0.18MB (URL Details)
23 Jan 2026 26 Jan 2026 Response Authority - Scottish Borders Council Exchange confirming availability 0.18MB (URL Details)
23 Jan 2026 26 Jan 2026 Response Cameron Purdie Exchange confirming availability 0.16MB (URL Details)
20 Jan 2026 20 Jan 2026 Correspondence DPEA to Agent - Pinsent Masons LLP, Council, MOD, Letter confirming revised date for PEM 0.15MB (URL Details)