NA-330-001 (Notified application)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=125898
 Hundland Hill (Land Near), Birsay, Orkney, KW17 2NR
 -3.2177240
 59.125046
 1027104
 330393
 Erect Four Wind Turbines (Maximum Height Of 180 Metres, Maximum Generation Capacity 26.4 Mw Total), A Substation And Maintenance Building, Create An Access, And Associated Infrastructure Including Access Tracks, Underground Cabling, Crane Hardstandings And Borrow Pit, Nisthill Wind Farm Limited.
 4
 180.00
 26.40
 27 Jan 2025
 27 Feb 2025
 Orkney Islands Council (22/320/TPPMAJ), Orkney Islands Council (22/320/TPPMAJ)
 Neil Collar
 Nisthill Wind Farm Limited
 Site Inspection, Further Written Submission, Inquiry
 Report
 Case on hold
 Murray, Claire (Tel: 01312448364 - Email: Claire.Murray2@gov.scot)
 Ms Alison Kirkwood
 07 Jul 2025
 04 Jun 2026
 **Case Update – 16/03/2026** The case has been placed on hold pending procedure notice responses.
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 5 of 5
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
15 Jul 2025 15 Jul 2025 Note of Meeting DPEA to Participating Parties Note of pre-examination meeting of 7 July 2025 0.14MB (URL Details)
15 Jul 2025 15 Jul 2025 Correspondence DPEA to Participating Parties Enclosing Note of pre-examination meeting of 7 July 2025 0.21MB (URL Details)
15 Jul 2025 15 Jul 2025 Correspondence DPEA to Participating Parties Clarifying request for views on conditions should be limited to matters relating to impacts on historic assets and places 0.19MB (URL Details)
13 Jun 2025 13 Jun 2025 Agenda DPEA to Participating Parties NA-330-001 PEM Agenda 7 July 2025 0.09MB (URL Details)
13 Jun 2025 13 Jun 2025 Correspondence DPEA to Participating Parties Notification of pre-examination meeting and enclosing agenda 0.16MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>