WIN-140-12 (Section 36 Wind Farm)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=126931
 Oliver Forest Wind Farm, Land North Of Menzion Farm, Tweedsmuir , ML12 6QP
 -3.4533010
 55.502939
 624200
 308300
 An Application Under Section 36 Of The Electricity Act For The Construction And Operation Of Oliver Forest Wind Farm, Total Of Seven Wind Turbines With A Maximum Blade Tip Height Of 200 M, Foundations, Crane Hardstandings And Adjacent Laydown Areas, Access Tracks, Watercourse Crossings, Temporary Borrow Pits, Temporary Construction Compounds, Substation And Control Building, Battery Energy Storage System, Ancillary Infrastructure And Heritage Footpath.
 7
 200.00
 73.40
 09 Sep 2025
 Scottish Borders Council (NA)
 Winston Roberts
 Oliver Forest Wind Farm Limited
 Inquiry
 Report
 Allocated to reporter
 Davidson, Rebecca (Tel: 01312448263 - Email: Rebecca.Davidson@scot.gov.uk)
 Tammy Swift-Adams
 10 Sep 2026
 04 Nov 2026
 **Case Update – 25/03/2026** Scottish Ministers have decided that they will determine this case, and a direction to that effect is available on the DPEA website. The appointed reporter will now prepare a report with recommendations for Ministers. The period for written submissions from members of the public has now closed and the authority has provided its response to the appeal. The reporter is looking at the documents and submissions and will consider what, if any, further procedures are necessary in order to consider this appeal. Further updates will follow in due course.
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 7 of 7
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
24 Apr 2026 24 Apr 2026 Response Cameron Purdie Confirming participation - Landscape and visual impact 0.21MB (URL Details)
17 Apr 2026 21 Apr 2026 Response Tweedsmuir Community Council Confirming participation - Landscape and visual impact 0.08MB (URL Details)
16 Apr 2026 16 Apr 2026 Response MOD Ministry of Defence confirming participation in oral sessions and FWS 0.23MB (URL Details)
07 Apr 2026 07 Apr 2026 Correspondence Authority Exchange suggesting dates for 2nd PEM and landscape hearing 0.29MB (URL Details)
07 Apr 2026 15 Apr 2026 Correspondence DPEA to applicant Exchange confirming procedure for the initial exchange on Eskdalemuir. 0.25MB (URL Details)
05 Feb 2026 05 Feb 2026 Correspondence DPEA to all 'opted in' parties Exchange confirming dates for inquiry and hearing sessions 0.17MB (URL Details)
05 Feb 2026 05 Feb 2026 Correspondence Authority Exchange confirming witness availability 0.28MB (URL Details)