PPA-270-2322 (Planning Permission Appeal)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=128419
 Land 2430M Sw Of Loch Buidhe, Bonar Bridge, IV24
 897458
 265053
 Carnaig Substation - Construction And Operation Of A 400Kv Substation And Associated Infrastructure, Site Access, And Landscaping
 Planning permission
 18 Feb 2026
 Highland Council (24/05062/FUL)
 04 Dec 2024
 09 Jan 2026
 Scottish Hydro Electric Transmission plc
 Mr Colin Hamilton
 Refusal of Application
 Written Submission, Further Written Submission
 Recalled
 Case on hold
 Murray, Claire (Tel: 01312448364 - Email: Claire.Murray2@scot.gov.uk)
 Ms Alison Kirkwood
 25 Aug 2026
 **Case Update – 14/04/2026** The case has been placed on hold pending procedure notice responses
 Substation/Transmission Line/Pipeline,
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
20 Apr 2026 20 Apr 2026 Correspondence DPEA to Agent -Gillespie Macandrew LLP and Author Advising of unaccompanied site inspection 0.15MB (URL Details)
20 Apr 2026 20 Apr 2026 Correspondence DPEA to Interested Parties Advising of unaccompanied site inspection 0.15MB (URL Details)
20 Apr 2026 21 Apr 2026 Correspondence DPEA to Interested Parties via post Advising of unaccompanied site inspection 0.19MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3