NA-330-001 (Notified application)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=125898
 Hundland Hill (Land Near), Birsay, Orkney, KW17 2NR
 -3.2177240
 59.125046
 1027104
 330393
 Erect Four Wind Turbines (Maximum Height Of 180 Metres, Maximum Generation Capacity 26.4 Mw Total), A Substation And Maintenance Building, Create An Access, And Associated Infrastructure Including Access Tracks, Underground Cabling, Crane Hardstandings And Borrow Pit, Nisthill Wind Farm Limited.
 4
 180.00
 26.40
 27 Jan 2025
 27 Feb 2025
 Orkney Islands Council (22/320/TPPMAJ), Orkney Islands Council (22/320/TPPMAJ)
 Neil Collar
 Nisthill Wind Farm Limited
 Site Inspection, Further Written Submission, Inquiry
 Report
 Allocated to reporter
 Murray, Claire (Tel: 01312448364 - Email: Claire.Murray2@scot.gov.uk)
 Ms Alison Kirkwood
 07 Jul 2025
 24 May 2026
 **Case Update – 01/06/2026** Further written information has been sought. Further details are available from the procedure notice on the case file.
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
13 Aug 2025 14 Aug 2025 Correspondence DPEA to Interested Parties and Consultees Advising of site inspections 0.16MB (URL Details)
14 Jul 2025 14 Jul 2025 Response Morton Fraser MacRoberts obo HES Confirming availability for HES to attend an accompanied visit of the World Heritage Site 0.27MB (URL Details)
09 Jul 2025 10 Jul 2025 Response Agent - Wright, Johnston & Mackenzie LLP Confirming availability for applicant witness to attend an accompanied visit of the World Heritage Site 0.24MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3