WIN-130-10 (Section 36 Wind Farm)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=125767
 An Carr Dubh Wind Farm, Located Between Inveraray To The South-East And Dalavich To The North-West, PA32
 -5.1650699
 56.249104
 710793
 204004
 An Application Under Section 36 Of The Electricity Act For The Construction And Operation Of The An Carr Dubh Wind Farm Comprising Of Up To 13 Wind Turbines, With A Maximum Blade Tip Height Of 180M
 13
 180.00
 85.80
 03 Dec 2024
 Argyll and Bute Council (N/A)
 
 Site Inspection, Further Written Submission, Inquiry, Hearing
 Report
 Allocated to reporter
 Davidson, Rebecca (Tel: 01312448263 - Email: Rebecca.Davidson@gov.scot)
 Mr Philip McLean
 05 Mar 2025
 21/08/2025 at Virtual Meeting
 18 Nov 2025
 **Case Update – 10/06/2025** Hearing sessions took place on 28 & 29 May 2025, and the webcasts can be viewed at www.dpea.public-i.tv. Further written submissions have been requested. An additional hearing session is scheduled for 21 August 2025 if the reporter decides it is required. Thereafter the report and recommendations will be finalised and submitted to Scottish Ministers as soon as possible.
 Wind Farm (two or more turbines),
 
contains

Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
29 May 2025 02 Jun 2025 Further Supporting Information Maurice O'Carroll OBO Authority Glasvaar Report of Handling 0.98MB (URL Details)
29 May 2025 02 Jun 2025 Further Supporting Information Maurice O'Carroll OBO Authority Glasvaar SEI Wirelines 3.13MB (URL Details)
29 May 2025 02 Jun 2025 Further Supporting Information Maurice O'Carroll OBO Authority Glasvaar Site Location Plan - Figure 1.1 0.83MB (URL Details)
29 May 2025 02 Jun 2025 Further Supporting Information Maurice O'Carroll OBO Authority Glasvaar Wind Farm - GWF1 & GWF2 - June 2024 1.84MB (URL Details)
16 Apr 2025 22 Apr 2025 Documents Ruaraidh Thompson OBO Authority WIN-170-2007 - Decision Notice 0.25MB (URL Details)
16 Apr 2025 22 Apr 2025 Documents Ruaraidh Thompson OBO Authority Determination - PLI Report 1.22MB (URL Details)
16 Apr 2025 22 Apr 2025 Documents Ruaraidh Thompson OBO Authority Upper Sonachan PLI Report 1.75MB (URL Details)
16 Apr 2025 22 Apr 2025 Documents Ruaraidh Thompson OBO Authority Upper Sonachan Decision Letter 1.50MB (URL Details)
11 Apr 2025 11 Apr 2025 Documents Applicant Updated Visualisations 72.90MB (URL Details)
07 Jan 2025 07 Jan 2025 Documents An Carr Dubh Wind Farm Ltd 221 - Argyll and Bute Landscape Wind Capacity Study 32.24MB (URL Details)

Click table headers to sort table