NA-330-001 (Notified application)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=125898
 Hundland Hill (Land Near), Birsay, Orkney, KW17 2NR
 -3.2177240
 59.125046
 1027104
 330393
 Erect Four Wind Turbines (Maximum Height Of 180 Metres, Maximum Generation Capacity 26.4 Mw Total), A Substation And Maintenance Building, Create An Access, And Associated Infrastructure Including Access Tracks, Underground Cabling, Crane Hardstandings And Borrow Pit, Nisthill Wind Farm Limited.
 4
 180.00
 26.40
 27 Jan 2025
 27 Feb 2025
 Orkney Islands Council (22/320/TPPMAJ), Orkney Islands Council (22/320/TPPMAJ)
 Fraser Gillies
 Nisthill Wind Farm Limited
 Further Written Submission, Inquiry, Hearing
 Report
 Allocated to reporter
 Devoy, Audrey (Tel: 0131 244 8182 - Email: Audrey.Devoy@gov.scot)
 Mrs Alison Kirkwood
 07 Jul 2025
 26 Mar 2026
 **Case Update – 13/06/2025** Further written information has been sought. Further details are available from the procedure notice on the case file. A virtual pre-examination meeting into this case will be held. The date can be viewed on the case website . Members of the public can view the proceedings at www.dpea.public-i.tv
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
27 Feb 2025 27 Feb 2025 Call-In Direction PARD Call-in and Direction 0.26MB (URL Details)