WIN-140-9 (Section 36 Wind Farm)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=124934
 Greystone Knowe Wind Farm, To The West Of The A7 Trunk Road On Land Approximately 2 Km South Of Heriot And 2.5 Km, West Of Fountainhall, TD1 2TH
 -2.9517766
 55.726603
 648543
 340319
 Proposed Onshore Wind Farm To Be Located In The Scottish Borders Comprising Of 14 Turbines, Hub Height 110 Metres And Each Turbine Will Have A Maximum Height To Blade Tip Up To 180 Metres
 14
 180.00
 01 May 2024
 Scottish Borders Council (N/A)
 Ms Amy Howard
 Greystone Knowe Wind Farm Ltd
 Site Inspection, Inquiry, Hearing
 Report
 Report Issued
 Brown, Christine (Tel: 0131 244 6866 - Email: Christine.Brown@gov.scot)
 Ms Sinead Lynch
 26 Mar 2025 at 10:00
 10 Oct 2024
 04 Jun 2025
 **Case Update – 03/06/2025** A report for this case has been submitted to Scottish Ministers. A decision by Scottish Ministers will be made in due course.
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1