PPA-140-2104 (Planning Permission Appeal)
https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=125403
Wull Muir Wind Farm, Land North Of Carcant Lodge, Near Heriot, EH38 5YE
654660
336253
Erection Of 8 No Wind Turbines With A Maximum Tip Height Of 150 Metres, Formation Of Access Tracks, Borrow Pit, Temporary Construction Compound, Erection Of Control Building, Onsite Substation, Associated Infrastructure And Energy Storage Compound
36.00
Planning permission
Scottish Borders Council (22/01960/FUL)
08 Jul 2024
Site Inspection, Further Written Submission
14 Jan 2025 (Appeal Allowed )
17 Feb 2026
Wind Farm (two or more turbines),