TRL-170-1 (Section 37 Transmission line)
https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=122044
Kendoon To Tongland 132Kv Reinforcement (Ktr) Project – Bg Route Deviation, Approximately 2 Km West And 1 Km South West Of, St John’S Town Of Dalry, DG7
579460
259820
Consent Under S37 Of The Electricity Act 1989 And Deemed Planning Permission Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 To Install And Keep Installed Overhead Electric Lines Described Collectively As The Kendoon To Tongland Reinforcement Project In Dumfries And Galloway Planning Authority Area
Dumfries and Galloway Council (N/A)
Site Inspection, Further Written Submission, Inquiry, Hearing
15 Jun 2022
**Case Update: 12/07/2023**
The hearing/inquiry sessions and further written submissions procedure have been completed. Closing submissions for all parties have been received and the inquiry has been formally closed. The reporters are currently preparing a report with their findings and recommendations. This will then be passed onto Scottish Ministers, who will make the final decision on this proposal.
Substation/Transmission Line/Pipeline,