WIN-270-16 (Section 36 Wind Farm)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=122308
 Cairn Duhie Wind Farm On Land Near Ferness, Nairnshire, Approximately 15Km South-East Of Nairn And 13.5Km North/North-West Of Grantown-On-Spey, Highland, PH26 3PX
 -3.7023237
 57.461471
 842522
 297973
 Application For Consent Under S36 Of The Electricity Act 1989 And Deemed Planning Permission Under S57(2) Of The Town And Country Planning (Scotland) Act 1997 For Cairn Duhie Wind Farm Located Within The Highland Council Planning Authority Area - Application Is For Consent For A Wind Farm With An Installed Capacity Of More Than 50Mw And Envisages A Development Of Up To 16 Wind Turbines At Up To 149.9 M To Blade Tip And Associated Infrastructure For A Period Of 35 Years
 16
 149.90
 67.20
 01 Jun 2022
 Highland Council (21/01521/S36)
 Mr Fraser Gillies
 
 Site Inspection, Inquiry, Hearing
 Report
 Decision issued
 Devoy, Audrey (Tel: 0131 244 8182 - Email: Audrey.Devoy@gov.scot)
 Ms Sinead Lynch
 Ms Karen Heywood
 06 Sep 2022
 05 Jun 2023
 02 Feb 2024 (Application Granted)
 **Case Update – 05/02/2024** The decision on this case has been issued. The case has been allowed and consent has been granted.
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
05 Dec 2022 05 Dec 2022 Correspondence DPEA and Agent - Wright, Johnston & Mackenzie LLP Exchange regarding site visits 0.22MB (URL Details)
21 Sep 2022 27 Sep 2022 Correspondence DPEA and Agent - Wright, Johnston & Mackenzie LLP Further exchanges regarding site visit 0.44MB (URL Details)
13 Sep 2022 16 Sep 2022 Correspondence DPEA and Authority Exchange regarding site visit locations and request for some to be accompanied 0.25MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3