PPA-140-2080 (Planning Permission Appeal)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=121020
 Land North Of Carcant Lodge, Wull Muir Wind Farm, Heriot, N/A
 -3.0179329
 55.781037
 654660
 336253
 Erection Of 8 No Wind Turbines With A Maximum Tip Height Of 130M, Formation Of Access Tracks, Borrow Pit, Temporary Construction Compound, Erection Of Control Building, Onsite Substation And Associated Infrastructure And Energy Storage Compound For Up To 4Mw
 Planning permission
 14 Apr 2020
 Scottish Borders Council (19/00191/FUL)
 11 Feb 2019
 03 Feb 2020
 Energiekontor UK Ltd
 Fraser Gillies
 Refusal of Application
 Site Inspection, Further Written Submission
 Decision
 Decision issued
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 Mr Stephen Hall
 11 Oct 2020
 19 Oct 2020 (Appeal Dismissed )
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
22 Jun 2020 22 Jun 2020 Documents List Agent - WJM LLP Updated appellant document list 220620 0.09MB (URL Details)
17 Jun 2020 18 Jun 2020 Documents Agent - WJM LLP APP007.028 - Millenderdale Decision Notice 16 April 2020 0.18MB (URL Details)
24 May 2020 26 May 2020 Further Supporting Information Agent - WJM LLP On behalf of Energiekontor UK Ltd 0.31MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3