PPA-190-2066 (Planning Permission Appeal)
https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=118330
Polquhairn Wind Farm , B7046 From Sinclairston To U728 Glenconner, Drongan, KA18
614728
247664
Construction, Operation And Decommissioning Of A 22.5 Megawatt (Mw) Wind Farm Comprising 9 (2.5Mw) Turbines Each With A Maximum Blade Tip Height Of 100 Metres And All Ancillary Infrastructure As Indicated In The Plans
Planning permission
East Ayrshire Council (14/0860/PP)
18 Aug 2017
Brookfield Renewable UK Ltd
Site Inspection, Further Written Submission
19 Sep 2018 (Appeal Allowed )
Wind Farm (two or more turbines),