PPA-170-2127 (Planning Permission Appeal)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=118260
 Annabaglish Wind Farm, Near Glenluce, Galloway, DG8 0LG
 -4.6769172
 54.886141
 557882
 228391
 Erection Of 14 Wind Turbines (Maximum Height Of 110M To Blade Tip), 1 Meteorological Mast, 1 Telecommunications Mast, 6 Temporary Meteorological Masts, Substation/Control Building And Temporary Construction Of Crane Hardstandings, Access Tracks And Associated
 Planning permission
 11 Oct 2017
 Dumfries and Galloway Council (13/P/1/0351)
 31 Oct 2013
 12 Jul 2017
 RES UK & Ireland Ltd
 Miss Kirsty Morris
 Refusal of Application
 Site Inspection
 Decision
 Decision issued
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 Mr Keith Bray
 03 Jan 2018
 26 Feb 2018 (Appeal Dismissed )
 Wind Farm (two or more turbines), Meteorological/Anemometrical Mast,
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 4 of 4
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
02 Feb 2018 02 Feb 2018 Further Supporting Information Agent - Eversheds Submissions on new documents 0.14MB (URL Details)
02 Feb 2018 02 Feb 2018 Documents Agent - Eversheds APP004.044 - Onshore Wind Policy Statement 0.44MB (URL Details)
10 Jan 2018 15 Jan 2018 Further Supporting Information Agent - Eversheds Enclosing final response from SEPA 0.16MB (URL Details)
11 Dec 2017 14 Dec 2017 Further Supporting Information Agent - Eversheds Enclosing correspondence from SEPA 0.12MB (URL Details)