WIN-270-8 (Section 36 Wind Farm)
 Bookmark
 http://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=117947
 Limekiln Wind Farm, Near Reay, Caithness, KW14
 -3.7533386
 58.529623
 961500
 298000
 Construct And Operate A Wind Farm Comprising Up To 24 Turbines With A Predicated Installed Capacity Of 72Mw And Related Ancillary Infrastructure
 07 Apr 2017
 Highland Council
 Miss Kirsty Morris
 Infinergy Ltd on behalf of Limekiln Wind Ltd
 Site Inspection, Further Written Submission, Inquiry, Hearing
 Allocated to reporter
 Robertson, Jane (Tel: 01324 696467 - Email: jane.robertson@gov.scot)
 Mr Christopher Warren
 Mr Andrew Fleming
 18 Oct 2017
 17 Nov 2017
 Wind Farm (two or more turbines),
 
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
04 Dec 2017 04 Dec 2017 Procedure Notice DPEA to Limekiln agent - Eversheds Sutherland (Int request for further written submissions 138KB Bookmark (URL Details)
27 Oct 2017 27 Oct 2017 Procedure Notice DPEA attaching note of pre-examination meeting 67KB Bookmark (URL Details)
contains

Please note that when searching for a topic, use the singular phrase e.g. "turbine" rather than "turbines" to ensure all relevant documents are returned

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 2 of 2