WIN-270-8 (Section 36 Wind Farm)
 Bookmark
 http://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=117947
 Limekiln Wind Farm, Near Reay, Caithness, KW14 7RR
 -3.7533386
 58.529623
 961500
 298000
 Construct And Operate A Wind Farm Comprising Up To 24 Turbines With A Predicated Installed Capacity Of 72Mw And Related Ancillary Infrastructure
 07 Apr 2017
 Highland Council
 Miss Kirsty Morris
 Infinergy Ltd on behalf of Limekiln Wind Ltd
 Site Inspection, Further Written Submission, Inquiry, Hearing
 Report Issued
 Robertson, Jane (Tel: 0131 244 6927 - Email: jane.robertson@gov.scot)
 Mr Christopher Warren
 Mr Andrew Fleming
 07 Mar 2018
 18 Oct 2017
 17 Nov 2017
 *Case update 16 October 2018* The report for this case was submitted to Scottish Ministers on 16 October 2018. A decision by Scottish Ministers will be made in due course.
 Wind Farm (two or more turbines),
 
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
08 Mar 2018 13 Mar 2018 Representations interested party Bisset, Danny Mr 38KB Bookmark (URL Details)
07 Mar 2018 13 Mar 2018 Representations interested party Sutherland, Oliver Mr 69KB Bookmark (URL Details)
07 Mar 2018 13 Mar 2018 Representations interested party Sutherland, Liam Mr 68KB Bookmark (URL Details)
contains

Please note that when searching for a topic, use the singular phrase e.g. "turbine" rather than "turbines" to ensure all relevant documents are returned

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 3 of 3