PPA-170-2102 (Planning Permission Appeal)
https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=117002
Land At Barwhillanty Estate And Glenswinton Farm, (Mochrum Fell Wind Farm), Parton, Castle Douglas
574913
272064
Erection Of 8 Wind Turbines (Maximum Height Up To 126.5M To Blade Tip (Turbines 1, 2, 3, 4, 6, 8 And 9) And 116.5M To Blade Tip (Turbine 5)) And Associated Works Including External Transformers, Control Buildings/Substation, Construction Of New Access Tracks (Including Improved Junction At A713) And Upgrade To Existing Forestry Tracks, 1 Permanent Anemometer Mast, 3 Temporary Construction Compounds, 3 Borrow Pits And Associated Infrastructure
(Amended To Remove 3 Turbines From The Proposal (For
Planning permission
Dumfries and Galloway Council (13/P/2/0327), Dumfries and Galloway Council
26 Jun 2015
Site Inspection, Further Written Submission
05 Jul 2016 (Appeal Allowed )
Wind Farm (two or more turbines),
Meteorological/Anemometrical Mast,