PPA-140-2053 (Planning Permission Appeal)
 https://www.dpea.scotland.gov.uk/CaseDetails.aspx?id=115751
 Land South East Of Halmyre Farmhouse (Hag Law), Romanno Bridge, Scottish Borders
 Construction Of Wind Farm Consisting Of 8 No. Turbines Up To 100M High To Tip With Associated External Transformers, Tracking, New Site Entrance Off A701, Borrow Pit, Underground Cabling, Substation And Compound And Temporary Construction Compound
 Planning permission
 30 Apr 2015
 Scottish Borders Council (14/00738/FUL)
 27 Jun 2014
 02 Feb 2015
 Engie (previously Stevenson Hill Wind Energy Ltd)
 Ms Louise Cockburn
 Refusal of Application
 Site Inspection, Further Written Submission, Hearing
 Recalled
 Decision issued
 Case Owner, DPEA (Tel: 0300 244 6668 - Email: dpea@gov.scot)
 DPEA Reporter
 DPEA Reporter
 04 Nov 2015
 08 Jul 2016 (Appeal Dismissed )
 Wind Farm (two or more turbines),
 
contains

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1
Go To Page:
Date Sent/Received Date of Publication Type of Publication Submitting Party Document Name Size
28 May 2015 Recall direction Recall Direction 0.04MB (URL Details)

Click table headers to sort table

  • <<
  • <
  • 1
  • >
  • >>
  • Displaying Results 0 - 1 of 1